COMMERCIAL AND INSTITUTIONAL PROJECTS
Burger King World Headquarters
$ 30,000,000 Completed 1986 – 2002
General Contractor / Design Build
(General Contractor of Record Main Building)
CEO, President Office & Vice President Offices
Executive Conference Room, Lounge, & Restrooms
Executive Offices (over 250 Complete to date)
Kitchen & Cafeteria
Finish Carpentry / Millwork Contract
Interior Contractor Data Center Computer Room
Air and Water Quality Remediation
ADA Restroom Upgrade
Contract Furniture
Diageo Headquarters
$ 5,000,000 Completed 1998 - Today
General Contractor / Design Build
(General Contractor of Record Main Building)
CEO, President Office & Vice President Offices
Executive Conference Room, Lounge, & Restrooms
Simmons Machine Tool Corp
$ 500,000 Completed 2004
Miami Tri-Rail
General Contractor / Design Build
Wheel turning machine (completed in 4 weeks)
Concrete foundation and supports for equipment
Pavarini Construction
2004 - Today
Acqualina Condo $ 2,500,000 Completed 2005
Concrete Repair Contractor (completed in 50 weeks)
360 Project Condo $ 1,800,000 Completed 2006
Concrete Repair Contractor (completed in 25 weeks)
Punch List
Asia Condo $ 2,200,000 Completed 2007
Concrete Repair Contractor (completed in 45 weeks)
Punch List
Turner Construction Corp
1993 - Today
Charlotte Regional Hospital
$ 2,500,000 Completed 2004
General trades except MEP (completed in 10 weeks)
Hurricane repair work
Support services for all trade (food, equipment, supplies, etc.)
Doral Golf Club
$ 1,800,000 Completed
General trades except MEP (completed in 13 weeks)
200 hotel restrooms
Telefutura TV Studio
$ 900,000 Completed
Structure Contractor (completed in 10 weeks)
Shore existing roof structure, Demo existing columns,
New foundation, columns and supports
United State Postal Service
$ 3,500,000 Completed
Process & Distribution Centers
General Contractor except MEP (completed in 50 weeks)
L.O.G. Modification Tray Management System
Northrop Grumman / Lockheed Martin (prime subcontractor)
Miami, Ft. Lauderdale and Miami Beach
Safety to Life Project
$ 12,000,000 Completed 2004
Miami – Dade Public schools over 15 school projects
General trades scope of work except MEP
Major school projects:
Palmetto High School
Merrick Educational School
Killian High School
Miami Senior High School
Circuit City
$ 9,000,000 Completed 2000
Demolition, Carpentry, Concrete & Doors and hardware (completed in 12 weeks)
West Palm Beach, Delray Beach and Boynton Beach
National Car Rental
$ 11,000,000 Completed 1988-1991
Miami (Phase I, II & III)
Construction Management
General Contractor
West Palm Beach (Phase I & II)
Construction Manager
General Contractor
Repair & Construction
Dade, Broward & Palm Beach
University of Miami
$ 9,000,000 Completed 1990 - 1995
General Contractor
Coral Gables and Jackson Hospital
New Elevator Shaft Structure Contractor
St. Thomas University
$ 7,500,000 Completed 1993 - 1997
General Contractor / Design Build
President Office & Board Room
Dean Offices
Law School Remolding Phase I & II
Dorm Building (115 Rooms remolded)
Cascia Hall
Sullivan Hall
University Inn
ADA Restroom repairs
Repairs & Remodeling
Computer Science Lab
Library
60 offices & classroom
Nortel (Northern Telecommunication)
Completed 1995 - 2008
General Contractor / Design Build
Executive Conference Room, Lounge, & Restrooms
Executive Offices (120 Complete to date)
Finish Carpentry / Millwork Contract
Data Center Computer Room
Parking Lot Expansion
Secure Communications Center
ADA Restroom Upgrade
Contract Furniture
Fine Art Lamps
$ 6,500,000 Completed 1996 - 1999
General Contractor / Design Build
ADA Upgrade
Office expansion
Building Connector’s
Automation Contractor (Overhead Line)
Facility ret-o-fix
Schering -Plough / Merk Laboratories
$ 9,500,000 Completed 1997-Today
General Contractor / Design Build
Building #3 Expansion
Hazardous Material Storage building
Solvent Locker
New Office Mezzanine
Production Mezzanine #4
NationsBank / Bank of America
$10,500,000 Completed 1996 - 2000
Operations Center, the Vault & Branch Offices
General Contractor / Design Build
Daycare facility upgrade
Office expansion
USA Broadcasting WAMI
$ 9,500,000 Completed 1999 - 2003
Operations Center, Transmitter Tower
General Contractor / Design Build
U.P.S. System Transmitter Tower
New satellite
Office expansion
South Miami Medical Square
$ 2,500,000 Completed 1988
Structure Contractor
5 Story Office Building
2 Story Parking Garage
City of Miami Orange Bowl
$ 1,800,000 Completed 1988
Structure Contractor
Elevator Tower
Sunset Suites
$ 1,500,000 Completed 1988
Structure Contractor
Three Story Office Building
Florida Power and Light
$ 500,000 Completed 1988
Sub Station (up-grade)
City of North Miami Beach
$ 2,000,000 Completed 1988
Norwood Water Treatment Plant
Structure Contractor
Chlorine gas storage